The Home Road Water Plant Drew No Bids. Dublin Road's Work Goes On

October 15, 2026

On August 26, 2026, Columbus opened bids for the main construction contract on the Home Road Water Plant and found it had received none. The plant sits on city-owned land at the southeast corner of Home Road and Dublin Road along the Scioto River. When it's built, it will be the first new water plant Columbus has constructed since the 1980s. A $1.6 billion project with no bidders sounds like a project on hold.

For anyone who drives SR 745, that's mostly not true. The empty bid opening delays the treatment plant. The digging, the hauling, the road widening and the planned roundabout at Home Road were never part of that contract. Each one is either already under contract or run by a different agency on its own timeline. Both the plant site and Tartan Fields are in Concord Township. The township's comprehensive plan lists Tartan Fields as a 444.9-acre, 598-lot development zoned in 1996. What follows explains which parts of the project actually affect the road.

What the empty bid opening put on hold

The city put the main contract out as a traditional design-bid-build job in February. When bids opened on August 26, no one had submitted one. Columbus then switched to a Construction Manager at Risk process. In that process, a contractor is picked first on qualifications, then shortlisted firms are asked for proposals. According to the city's September 14, 2026 contractor presentation, the request for qualifications was expected the week of October 12, 2026. Requests for proposals to shortlisted firms would follow in December 2026 or January 2027.

The new process changes the earlier timeline. A December 2025 schedule expected a notice to proceed in November 2026, substantial completion in 2032 and final completion in 2033. The September presentation does not give a new notice-to-proceed date. That makes the November 2026 start effectively expired, and the 2032 and 2033 completion dates are now best read as forecasts set before the procurement change.

The same presentation lists the plant's scope at 24 structures, an estimated 147,000 cubic yards of cast-in-place concrete and a $1.6 billion project budget.

The $107.6 million contract that was never waiting

Site preparation has been under a separate contract all along. Columbus City Council approved a site-preparation contract with Kokosing Industrial, Inc. on December 16, 2024, for $107,626,136.01 plus $2,000 for prevailing-wage services. Notice to proceed came in February 2025, and substantial completion is scheduled for July 2028. That is about 7 percent of the plant budget, and it covers nearly all the work that touches SR 745.

The September presentation lists the scope:

  • Grading for and construction of a 138kV electrical substation
  • Site clearing and tree removal
  • Demolition of existing utilities, pavement and buildings
  • Bedrock removal, about 450,000 cubic yards of overburden and 270,000 cubic yards of rock
  • Widening Dublin Road, with dedicated turn lanes for plant access
  • Sediment and erosion control, plus storm sewers

The road widening and turn lanes are the items most likely to affect a daily drive. The city's project FAQ says traffic impacts from the plant will be minor, mainly while the new SR 745 access turn lanes are built. As of this writing, no lane-closure dates or flagging schedule for that work have been published in the project materials.

The two official sources give slightly different end dates for site prep. The FAQ says early site preparation will be complete by early 2029, while the September presentation puts the contract's substantial completion at July 2028. The sources don't explain the gap. Either way, the site work runs at least into 2028, whatever happens with the main plant.

Where 270,000 cubic yards of rock goes

The FAQ names two haul routes for the removed rock. The contractor chose them based on where two nearby quarries sit, to the west and north of the site:

  1. Dublin Road to Moore Road
  2. Dublin Road to US 42 to S. Section Line Road

Both routes start on Dublin Road. The FAQ also records a question about whether a haul route other than Moore Road was considered. The city's answer is that the routes follow the quarry locations. A June 4, 2025 public presentation on controlled blasting said major access routes should limit use of local roads. It listed US 42, SR 745, Home Road, Moore Road and S. Section Line Road as the roads to the quarries.

The materials address the hours in two places. The same presentation planned blasting generally between 9 a.m. and 4 p.m., depending on safety, weather and site conditions. The FAQ says the city doesn't expect night shifts. Neither source gives truck counts or a set hauling schedule, so the daytime window applies to blasting, not to every truck.

Once the plant is running, the FAQ expects about six chemical delivery trucks a day. That figure describes the plant in operation, years from now, not construction traffic.

A roundabout on a separate schedule

The other big change at Home Road and SR 745 doesn't depend on the plant contract at all. The Delaware County Engineer's project page, dated July 29, 2026, describes a single-lane modern roundabout at the intersection. It cites traffic delays and unsafe bike and pedestrian crossings as the reasons. Construction is estimated at $2.2 million. The September plant presentation also lists "Roundabout at SR 745 & Home Road" as a related project.

The sources disagree on who is leading the project. The County Engineer's page names its own office as the contact. The city's FAQ credits ODOT District 6 with planning the roundabout. No source found during research settles which agency will deliver it.

Here is how the separate timelines compare:

Project Who it belongs to Where it stands Next milestone
Site prep, Dublin Road widening, turn lanes Columbus, Kokosing Industrial contract Under way since February 2025 Substantial completion July 2028
SR 745 and Home Road roundabout Delaware County Engineer page; city FAQ credits ODOT District 6 Design complete Right-of-way 2026–27, utilities 2027–28, construction 2028
Main treatment plant Columbus, CMAR contractor not yet chosen No bids August 26, 2026 RFQ week of October 12; RFP December 2026 or January 2027

If both keep to schedule, 2028 is the year the roundabout gets built and the site-prep contract reaches substantial completion. Neither date depends on who wins the plant contract this winter.

The site also holds a piece of local history. The Ohio Home Cemetery on the property will be preserved, and people can visit it during construction by appointment.

Meanwhile, at Glick Road

South of the plant, another long-watched corner is also waiting on a new plan. In February 2026, Rise Brands dropped its proposed golf-themed entertainment campus at the former Bogey Inn, 6013 Glick Road. NBC4 reported that the company's CEO told The Columbus Dispatch the project wasn't feasible at the site. She added that the company was still interested in a golf-related concept. The Dispatch's own report described the abandoned plan as a three-acre entertainment destination. In May, Columbus Business First reported that Muirfield Village Golf Club was preparing a request for proposals to bring a new user to the site. No sale, tenant or demolition had been confirmed in the sources reviewed.

Where updates will show up first

The city points people to the project website and its regularly updated FAQs for progress reports. The resources page archives past sessions. Those include a Dublin City Council briefing on March 9, 2026, neighborhood meetings on June 18 and June 22, 2026, and the September 14 contractor meeting where the no-bid result was presented. For questions, Columbus Water & Power's hotline is 614-645-2675. The Water Supply Engineering office answers Home Road Water Plant questions at 614-645-7100. The next milestone to watch for is the request for qualifications, expected the week of October 12.

Big public projects near home bring up practical questions, from what a 2028 roundabout means for an everyday drive to how long-term construction might come up if you sell. Oliver Chapman follows the Dublin Road corridor closely and is glad to talk through the timelines with you. Let's Connect.

A Relationship-Driven Approach

Oliver Chapman is committed to building lasting relationships through honest communication, local expertise, and personalized service tailored to every client. From first-time buyers to experienced investors, clients receive dedicated support designed to simplify every step of the real estate process. Contact Oliver today to discuss all your real estate needs!